ASX ANNOUNCEMENT
29 APRIL 2026
ASX:CPO OTCID:CPORF
QUARTERLY ACTIVITIES REPORT
FOR THE PERIOD ENDED 31 MARCH 2026
Culpeo Minerals Limited (Culpeo or the Company) (ASX: CPO, OTCID: CPORF) provides an update
on its activities for the quarter ended 31 March 2026 (the Quarter).
ACTIVITY HIGHLIGHTS
LANA CORINA PROJECT
• Earn-In amended, material reducing near-term cash payment requirements from US$750,000 to
US$150,000 while preserving the pathway to 80% ownership.1
• Progress continued on securing a revised long-term land Access Agreement. While timing has
extended beyond initial expectations, the Company remains focused on establishing a durable
access framework to support ongoing and repeat drilling campaigns.
• Fully-funded 4,000m diamond drilling programme at Vista Montana targeted to commence in
Q2 2026, subject to final approvals.
FORTUNA PROJECT
• Large-scale porphyry-style copper system defined over a 1.7km by 500m corridor remains an
exciting follow-up drill target at the La Florida Prospect where ongoing geological interpretation
and targeting has defined a high-priority drill target.
CORPORATE
• Unmarketable Parcel sale facility launched to streamline the share register and reduce costs.2
• All resolutions passed at General Meeting of Shareholders held on 27 January 2026.
• Cash position of A$2.8 million at Quarter end with no debt.
CULPEOMINERALS.COM.AU
ASX ANNOUNCEMENT 29 APRIL 2026
PAGE |2
Figure 1: Culpeo Minerals primary project areas, located approximately 350km north of Santiago Chile
CULPEOMINERALS.COM.AU
ASX ANNOUNCEMENT 29 APRIL 2026
PAGE |3
ACTIVITY DETAIL
LANA CORINA PROJECT
Earn-In Agreement Amendment
The Company successfully renegotiated the Lana Corina earn-in schedule during the Quarter,
delivering a material improvement in near-term cash outflows while maintaining full exposure to the
Project upside. Key terms include1
:
• Reduction in near-term payments from US$750,000 to US$150,000.
• Deferral of certain mid-term payment obligations.
• No change to total acquisition consideration.
Culpeo retains the right to increase its ownership to an 80% aggregate interest in the Project,
including a right of first refusal over the remaining 20% interest. The Company has already satisfied
the expenditure requirements to earn a 50% interest in the Project.
Figure 2: Lana Corina Project (Chile)
Access Agreement and Upcoming Drilling
Progress continued on securing a revised long-term land Access Agreement with the Soruco
community. While timing has extended beyond initial expectations, the Company remains focused
on establishing a durable access framework to support ongoing and repeat drilling campaigns.
A fully funded 4,000m diamond drilling programme at the Vista Montana Prospect is expected to
commence in Q2 2026, subject to completion of access agreements.
The programme is designed to test the 3km interpreted mineralised corridor linking Lana Corina to
Vista Montana, targeting extensions to known mineralisation and potential new discovery zones
along this extensive trend.
CULPEOMINERALS.COM.AU
ASX ANNOUNCEMENT 29 APRIL 2026
PAGE |4
FORTUNA PROJECT
The Fortuna Project is located approximately 350km north of the Chilean capital Santiago, and 25km
north of Culpeo’s complementary Lana Corina Project. Fortuna hosts numerous historical small-scale
workings that targeted near-surface, high-grade mineralisation (Figure 3). The Project area lies within
the Coastal Cordillera, a prolific porphyry belt that hosts multiple major copper deposits.
Figure 3: Culpeo Minerals primary project areas, with significant trenching and drilling results1
CULPEOMINERALS.COM.AU
ASX ANNOUNCEMENT 29 APRIL 2026
PAGE |5
Work during the Quarter was focused on follow up mapping and rock chip sampling at La Florida
and the surrounding area. In addition, an appraisal was undertaken of the maiden geochemically
mapping, rock chip sampling, trenching and drilling to vector in and develop additional drill targets.
CORPORATE ACTIVITY
Unmarketable Parcel Sale Facility
During the Quarter, the Company established a share sale facility for holders of unmarketable parcels,
defined as shareholdings valued at less than A$500 (Unmarketable Parcels) as at 16 January 2026.2
Approximately 416 shareholders were identified as holding Unmarketable Parcels, representing a
total of approximately 4.55 million shares. Under the facility, the Company will cover all costs
associated with the sale and transfer of these shares, excluding any tax implications, which remain
the responsibility of the individual Shareholders.
The facility is intended to assist Shareholders in realising the value of their holdings without incurring
brokerage or other transaction costs, while also reducing the administrative burden and costs
associated with maintaining a large number of small shareholdings.
Euroz Hartleys Group has been appointed to facilitate the sale process.
Results of General Meeting
A General Meeting of Shareholders was held on 27 January 2026, with all resolutions passed by the
requisite majorities.
Cash Position at Quarter End
At Quarter end, Culpeo held A$2.8 million in cash and zero debt.
This announcement has been authorised by the Board of Directors of Culpeo Minerals Limited.
CONTACT
Geoff McNamara
Interim Executive Chairman
E: geoff.mcnamara@culpeominerals.com.au
P: +61 (08) 6383 7894
CULPEOMINERALS.COM.AU
ASX ANNOUNCEMENT 29 APRIL 2026
PAGE |6
ABOUT CULPEO MINERALS LIMITED
Culpeo Minerals Limited is a copper-focused exploration and development company with a strategic portfolio
of high-quality assets located in Chile, the world’s leading copper-producing jurisdiction. The Company is
targeting high-grade copper systems within Chile’s infrastructure-rich Coastal Cordillera, a proven belt hosting
multiple major copper deposits.
Culpeo has delivered a significant copper and molybdenum discovery at the Lana Corina Project and continues
to systematically advance its highly prospective Fortuna Project. These assets form the basis of a focused
growth and discovery strategy aiming at unlocking district-scale potential through disciplined exploration and
staged project advancement.
The Lana Corina and Fortuna Projects are located in Chile’s Coquimbo Region, approximately 350 kilometres
north of Santiago, in proximity to the world-class Los Pelambres mine. Both projects host extensive
outcropping copper mineralisation and are situated in areas supported by well-developed infrastructure,
including road access, power transmission, water availability and a skilled local mining workforce - factors
critical in enabling cost-effective and efficient development
The Company is led by a highly experienced Board and management team with a strong track record of
exploration success and operational delivery in Chile. Culpeo’s strategy is centred on creating shareholder value
through the discovery and development of high-grade, near-surface copper systems in a tier one mining
jurisdiction, supported by a clear pathway to development and scalability.
CULPEOMINERALS.COM.AU
ASX ANNOUNCEMENT 29 APRIL 2026
PAGE |7
COMPETENT PERSONS’ STATEMENTS
The information in this report that relates to Exploration Results is based on information compiled by Mr
Zeffron Reeves (B App Sc (Hons) Applied Geology) MBA, MAIG). Mr Reeves is a member of the Australian
Institute of Geoscientists and a Director and shareholder of the Company. Mr Reeves has sufficient experience
that is relevant to the style of mineralisation and type of deposit under consideration and to the activity which
he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Reeves consents to the inclusion in
this report of the matter based on this information in the form and context in which it appears.
The information in this announcement that relates to the historic Exploration Results as listed in the table below
is based on, and fairly represents, information and supporting documentation prepared by the Competent
Person whose name appears in the same row, who is a Director or shareholder of or independent consultant
to the Company and is a Member of the Australasian Institute of Mining and Metallurgy (AusIMM), Australian
Institute of Geoscientists (AIG), Australian Society of Exploration Geophysics (ASEG), or a Recognised
Professional Organisation (RPO). Each person named in the table below has sufficient experience which is
relevant to the style of mineralisation and types of deposits under consideration and to the activity which he
has undertaken to quality as a Competent Person as defined in the 2012 Edition of the Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves.
Activity Competent Person Membership Status
Exploration Results (until 31 Oct 2024) Mr Maxwell Tuesley (Shareholder and former Director) AusIMM Member
Exploration Results (after 31 Oct 2024) Mr Zeffron Reeves (Director and Shareholder) AIG Member
The Company confirms that it is not aware of any new information or data that materially affects the Exploration
Results and Geophysical Results information included in previous announcements. The Company confirms that
the form and context in which the applicable Competent Persons’ findings are presented have not been
materially modified from the previous announcements.
FORWARD-LOOKING STATEMENTS
This document may include forward-looking statements. Forward-looking statements include, but are not
limited to, statements concerning Culpeo Minerals Limited’s planned exploration programme and other
statements that are not historical facts. When used in this document, the words such as "could," "plan,"
"estimate," "expect," "intend," "may”, "potential," "should," and similar expressions are forward-looking
statements. Although Culpeo Minerals Limited believes that its expectations reflected in these forward-looking
statements are reasonable, such statements involve risks and uncertainties, and no assurance can be given that
actual results will be consistent with these forward-looking statements.
CULPEOMINERALS.COM.AU
ASX ANNOUNCEMENT 29 APRIL 2026
PAGE |8
Appendix A: Culpeo Minerals Exploration Concessions at 31 March 2026
Project Licence Company Area (Ha) Grant Expiry Ownership
Lana - Corina San Agustin SCM Antares 1 1951 None 50%
Socavon SCM Antares 1 1951 None 50%
Lana Segunda SCM Antares 1 1951 None 50%
Corina SCM Antares 1 1951 None 50%
Laco 1 al 10 SCM Antares 10 2015 None 50%
Sara 1 – 20 Antofagasta Minerals 90 2006 None 50%
Patty 2 1 – 75 SCM Antares 75 2019 None 50%
Patty 3 1 – 260 SCM Antares 260 2019 None 50%
Patty 4 1 - 111 SCM Antares 111 2019 None 50%
Total – Lana Corina 550 Ha
Petacas Peta 31/55 EM DOS 120 11-Nov-89 None 66%
Peta 91/92 EM DOS 10 11-Nov-89 None 66%
Peta 15/28 EM DOS 70 06-Nov-89 None 66%
La Rosa 27/28 EM DOS 6 26-Dec-89 None 66%
La Rosa 31/46 EM DOS 80 28-Jun-11 None 66%
La Rosa 1/30 EM DOS 300 25-Nov-91 None 66%
Corredor 2, 1/12 EM DOS 12 18-Feb-15 None 66%
Corredor 3, 1/6 EM DOS 6 18-Feb-15 None 66%
Cachorro 1/20 EM DOS 20 11-Nov-14 None 66%
Cachorro 1,1/160 EM DOS 160 28-Jul-15 None 66%
Cachorro 2, 1/95 EM DOS 95 18-Feb-15 None 66%
Cachorro 3, 1/24 EM DOS 242 18-Feb-15 None 66%
Cachorro 4, 1/173 EM DOS 173 18-Feb-15 None 66%
Cachorro 5, 1/87 EM DOS 87 18-Feb-15 None 66%
Almudena 1,1 EM DOS 1 22-May-15 None 66%
Amudena 2, 1/3 EM DOS 3 22-May-15 None 66%
Almudena 3, 1/2 EM DOS 2 22-May-15 None 66%
Almudena 4, 1/7 EM DOS 7 22-May-15 None 66%
Almudena 5, 1/6 EM DOS 6 22-May-15 None 66%
Almudena 6,1 EM DOS 1 22-May-15 None 66%
Almudena 7,1 EM DOS 1 22-May-15 None 66%
Almudena 8,1/4 EM DOS 4 22-May-15 None 66%
Total – Las Petacas 1,406 Ha
San Sebastian San Sebastian 1/16 (2/16) Minera Panga SpA 45 1998 None 100%
San Sebastian 1/16 (1) Minera Panga SpA 5 1998 None 100%
Total – San Sebastian 50 Ha
Fortuna LA FLORIDA 1 a 20 SCM Antares 100 2007 None 80%
LA FLORIDA II 1 al 20 SCM Antares 100 2010 None 80%
PIEDRA DURA 1 a 20 SCM Antares 96 2006 None 80%
EL QUILLAY 5A 1 al 17 SCM Antares 17 2011 None 80%
EL QUILLAY 4A 1 al 25 SCM Antares 25 2011 None 80%
Bastis 29CB 1 al 16 SCM Antares 127 2011 None 80%
Bastis 29CB 17 al 20 SCM Antares 35 2011 None 80%
LOS QUILLAYES 1/4 (3/4) SCM Antares 10 1984 None 80%
LA ESPERANZA 1/10 SCM Antares 50 1960 None 80%
PRETECATEMO 1/20 SCM Antares 100 1953 None 80%
Antares 1 al 165 SCM Antares 165 2011 None 80%
MATILDE 2 1 al 50 SCM Antares 200 2011 None 80%
El Quillay 2 1 al 224 SCM Antares 224 2011 None 80%
El Quillay 3 1 al 236 SCM Antares 236 2011 None 80%
El Quillay 4A 1 al 89 SCM Antares 89 2011 None 80%
El Quillay 4B 1 al 40 SCM Antares 40 2011 None 80%
El Quillay 5A 1 SCM Antares 1 2011 None 80%
El Quillay 5C 1 al 98 SCM Antares 98 2011 None 80%
El Quillay 6 1 al 13 SCM Antares 13 2011 None 80%
El Quillay 6A 1 al 7 SCM Antares 7 2011 None 80%
La Escondida 1-14 SLM La Escondida 42 2005 None 80%
FLORIDA 1 Culpeo Mining Chile Spa 300 02/05/2024 15/03/2026 100%
FLORIDA 10 Culpeo Mining Chile Spa 300 02/05/2024 15/03/2026 100%
FLORIDA 11 Culpeo Mining Chile Spa 300 02/05/2024 15/03/2026 100%
FLORIDA 12 Culpeo Mining Chile Spa 300 02/05/2024 15/03/2026 100%
FLORIDA 2 Culpeo Mining Chile Spa 300 02/05/2024 15/03/2026 100%
FLORIDA 3 Culpeo Mining Chile Spa 300 02/05/2024 21/02/2026 100%
FLORIDA 4 Culpeo Mining Chile Spa 300 02/05/2024 21/02/2026 100%
FLORIDA 5 Culpeo Mining Chile Spa 300 02/05/2024 13/02/2026 100%
FLORIDA 6 Culpeo Mining Chile Spa 300 02/05/2024 13/02/2026 100%
FLORIDA 7 Culpeo Mining Chile Spa 300 02/05/2024 14/02/2026 100%
FLORIDA 8 Culpeo Mining Chile Spa 300 02/05/2024 14/02/2026 100%
FLORIDA 9 Culpeo Mining Chile Spa 300 02/05/2024 20/02/2026 100%
Total – Fortuna 5,375 Ha
CULPEOMINERALS.COM.AU
ASX ANNOUNCEMENT 29 APRIL 2026
PAGE |9
Appendix B: Technical Details
Copper Equivalent (CuEq) values: Assumed commodity prices for the calculation of CuEq is Cu
US$3.00/lb, Au US$1,700/oz, Mo US$14/lb and Ag US$20/oz. Recoveries are assumed from similar
deposits: Cu = 85%, Au = 65%, Ag = 65%, Mo = 80%, Cu Eq (%) was calculated using the following
formula: ((Cu% x Cu price 1% per tonne x Cu recovery) + (Au(g/t) x Au price per g/t x Au recovery) +
(Mo ppm x Mo price per g/t x Mo recovery) + Ag ppm x Ag price per g/t x Ag recovery)) / (Cu price
1% per tonne x Cu recovery). Cu Eq (%) = Cu (%) + (0.54 x Au (g/t)) + (0.00037 x Mo (ppm)) + (0.0063
x Ag (ppm)). It is the Company’s opinion that all elements included in the metal equivalents have a
reasonable potential to be recovered and sold.
Appendix C: References
1.
Refer to ASX announcement dated 16 March 2026 “Culpeo Improves Terms of Lana Corina Earn-In”.